F.M. Woods WTP Upgrades

C3W was retained by the City of Guelph for the conceptual design for a two-phase upgrade being completed at the F.M. Woods WTP.

The first phase of the project involves converting the original pump station facility (ca.1879), which was designated as a City Heritage property in 1997, into office space for technical services and conservation staff.   The second phase of the project will see the construction of a replacement 1050 L/s pump station and wet well, replacement of the electrical power supply and distribution system, refurbishment of existing O&M facilities, construction of a new administration building and associated controls upgrades. 

The F.M. Woods WTP is the City of Guelph’s most critical water facility, treating and distributing up to 80% of the City’s water supply.   It also houses supply & distribution O & M and administration teams.  Transition planning was a key consideration.

The capital cost estimate for the project is $20M and it is anticipated to take three years to deliver. 

  View/Download pdf

Leave a Reply

Your email address will not be published. Required fields are marked *